Homes of Heritage Ltd v Cunningham and Others
| Jurisdiction | Ireland |
| Court | High Court |
| Judge | Mr Justice Liam Kennedy |
| Judgment Date | 19 December 2025 |
| Neutral Citation | [2025] IEHC 724 |
| Docket Number | [Record No. 2011/7436P] |
[2025] IEHC 724
[Record No. 2011/7436P]
THE HIGH COURT
Specific performance – Inordinate and inexcusable delay – Specific prejudice – Applicants seeking orders dismissing the claim against them for delay – Whether the applicants had shown specific prejudice
Facts: The second, third and fourth defendants, Mses Bredin (the applicants), on the advice of the first defendant, Mr Cunningham, joined him in two simultaneous transactions with the plaintiff, Homes of Heritage Ltd. In one transaction, the four defendants agreed to buy land from the plaintiff for €5,750,000 pursuant to a written agreement dated 13 April 2006. The plaintiff sought specific performance of that agreement. The applicants applied to the High Court for orders dismissing the claim against them for delay. The first defendant was not a party to the motion. The motion parties agreed that the Supreme Court’s judgment in Kirwan v Connors & Ors [2025] IESC 21 governed the approach to such applications, but disagreed as to its interpretation and its impact on the law as previously understood on the basis of Primor Plc v Stokes Kennedy Crowley [1996] 2 IR 459, and subsequent decisions. The applicants said that the claim should be dismissed for inordinate and inexcusable delay, particularly in the 2017 to 2024 period (on top of delay before proceedings commenced). They said that, although they need not show specific prejudice post-Kirwan, they had done so. While acknowledging some delay, the plaintiff sought to largely defend the prosecution of the proceedings. However, it primarily opposed the application based on its interpretation of Kirwan as requiring an uninterrupted two years’ delay immediately before the issuing of the motion.
Held by Kennedy J that whether it had a good case or not, the plaintiff had itself to blame for failing to pursue the matter. He held that its delays were even more intolerable than in Kirwan and the observations expressed in para. 200 of Hogan J’s judgment in that case would equally apply in this case. Kennedy J held that it would be unjust to the applicants to allow the claim to proceed. He noted that in addition to the pre-commencement delay, the plaintiff delayed for approximately eight years without a meaningful excuse. Although the specific prejudice demonstrated by the applicants was moderate (as in Kirwan), he found that there was undoubtedly general prejudice in terms of fading memories etc. He held that the application must succeed in the light of Kirwan.
Kennedy J held that the balance of justice required dismissal, and he would accordingly grant the reliefs sought in the application and dismiss the proceedings (as against the applicants alone) pursuant to Order 122, rule 11 of the Rules of the Superior Courts and/or the inherent jurisdiction.
Proceedings dismissed.
JUDGMENT of Mr Justice Liam Kennedy delivered on 19 December 2025 .
. The second, third and fourth defendants (“the applicants”) have applied for orders dismissing the claim against them for delay. The first defendant is not a party to the motion 1. The motion parties agree that the Supreme Court's recent judgment in Kirwan v Connors & Ors [2025] IESC 21 ( Kirwan) now governs the approach to such applications, but disagree as to its interpretation and its impact on the law as previously understood on the basis of Primor Plc v Stokes Kennedy Crowley [1996] 2 IR 459 ( Primor), and subsequent decisions.
. The applicants say that the claim should be dismissed for inordinate and inexcusable delay, particularly in the 2017 to 2024 period (on top of delay before proceedings commenced). They say that, although they need not show specific prejudice post- Kirwan, they have done so. While acknowledging some delay, the plaintiff seeks to largely defend the prosecution of the proceedings. However, it primarily opposes the application based on its interpretation of Kirwan as requiring an uninterrupted two years' delay immediately before the issuing of the motion. I consider that the proceedings should be dismissed for reasons set out below.
. As the authorities, including those cited by the applicants 2, show, recognising their constitutional obligations and the need to comply with Ireland's European Convention on
“ Justice may require that a claim of wrongdoing be advanced and adjudicated upon, but it also demands that it should be resolved within some reasonable timescale by reference to the event the subject matter of the proceedings.”
. Kirwan focused, inter alia, on the overlapping jurisdictions invoked by such motions — the inherent jurisdiction to dismiss for inordinate and inexcusable delay in the prosecution of the action (and references in this judgment to the Inherent Jurisdiction are to this aspect of the inherent jurisdiction 3) and/or the jurisdiction under Order 122, rule 11 (“Order 122”) of the Rules of the Superior Courts (“RSC”). The applicants invoke both jurisdictions.
. Order 122 is in the following terms:
“In any cause or matter in which there has been no proceeding for one year from the last proceeding had, the party who desires to proceed shall give a month's notice to the other party of his intention to proceed.
In any cause or matter in which there has been no proceeding for two years from the last proceeding had, the defendant may apply to the Court to dismiss the same for want of prosecution, and on the hearing of such application the Court may order the cause or matter to be dismissed accordingly or may make such order and on such terms as to the Court may seem just. A motion or summons on which no order has been made shall not, but notice of trial although countermanded shall, be deemed a proceeding within this rule.”
. The Supreme Court's decision in ( Collins v. Dublin Bus Unreported, 22 October 1999) ( Collins) highlighted the distinction between Order 122 and the Inherent Jurisdiction. Its facts, summarised by Murray J at paragraph 35 of Kirwan, are analogous to this case in key respects. After the High Court dismissed a claim ‘for want of prosecution’ it was argued on appeal that – despite the eleven-year delay since the alleged events giving rise to the action — the Court could not entertain an Order 122 application because it had not been preceded by two years of inactivity as required by that provision. There had been some, albeit minimal and desultory, activity on the plaintiff's part in the period preceding the application. The Supreme Court dismissed the appeal, considering the motion not under Order 122 but as “a similar but distinct application … to dismiss for reasons of delay – delay which was both
inordinate and inexcusable and prejudicial to the Defendants”. It noted that that distinction had been recognised in many cases and that Irish Courts had an inherent jurisdiction to control their own procedure and to dismiss a claim when the interests of justice so required.. Butler J summarised the pre- Kirwan position in Campbell v Geraghty [2022] IEHC 241, contrasting the overlapping jurisdictions, noting at paragraphs 17 & 18 that Primor:
“requires the court to consider whether there has been inordinate and inexcusable delay on the part of the plaintiff in prosecuting the proceedings. …
If… the court is satisfied that the delay is both inordinate and inexcusable, then it must then consider whether the balance of justice lies in favour of or against the dismissal of the proceedings.
The plaintiff bears the onus of establishing that, notwithstanding culpable delay on her part, the balance of justice nonetheless requires that she be permitted to continue her litigation.
In Primor, Hamilton CJ set out a number of factors which may be relevant to where the balance of justice might fie. These include
• delay on the part of the defendant;
• whether delay or other conduct on the part of the defendant amounts to acquiescence in the plaintiffs delay;
• whether the delay is such that it is no longer possible to have a fair trial
• whether serious prejudice has been caused to the defendant. That prejudice is not necessarily limited to prejudice in the defence of the proceedings but in fact that is the only prejudice raised by the defendant in this case.”
. In Kirwan, while unanimously endorsing the Court of Appeal and High Court's decisions to dismiss a claim for want of prosecution, the Supreme Court modified the approach to such applications. The events giving rise to the proceedings allegedly occurred in 2005/2006 but (two) proceedings only issued in 2012 and 2013. There was no further activity until August 2018, when a group of defendants (the Buttle defendants) applied to dismiss the 2013 proceedings for want of prosecution. In November 2018, after the plaintiff issued cross-motions, the other defendants, the solicitor defendants, issued a corresponding want of prosecution motion, as outlined in paragraph 3 of O'Donnell CJ's decision.
. The Supreme Court determined that the Primor test should be modified in the light of increasing concerns about the detrimental impact on the administration of justice of delays in prosecuting litigation, coupled with concerns as to the complexity and subjectivity of the Primor test. The importance of the issue was reflected in the fact that, having first been heard by a smaller panel, the appeal was re-argued before an expanded panel. O'Donnell CJ and...
Get this document and AI-powered insights with a free trial of vLex and Vincent AI
Get Started for FreeUnlock full access with a free 7-day trial
Transform your legal research with vLex
-
Complete access to the largest collection of common law case law on one platform
-
Generate AI case summaries that instantly highlight key legal issues
-
Advanced search capabilities with precise filtering and sorting options
-
Comprehensive legal content with documents across 100+ jurisdictions
-
Trusted by 2 million professionals including top global firms
-
Access AI-Powered Research with Vincent AI: Natural language queries with verified citations
Unlock full access with a free 7-day trial
Transform your legal research with vLex
-
Complete access to the largest collection of common law case law on one platform
-
Generate AI case summaries that instantly highlight key legal issues
-
Advanced search capabilities with precise filtering and sorting options
-
Comprehensive legal content with documents across 100+ jurisdictions
-
Trusted by 2 million professionals including top global firms
-
Access AI-Powered Research with Vincent AI: Natural language queries with verified citations
Unlock full access with a free 7-day trial
Transform your legal research with vLex
-
Complete access to the largest collection of common law case law on one platform
-
Generate AI case summaries that instantly highlight key legal issues
-
Advanced search capabilities with precise filtering and sorting options
-
Comprehensive legal content with documents across 100+ jurisdictions
-
Trusted by 2 million professionals including top global firms
-
Access AI-Powered Research with Vincent AI: Natural language queries with verified citations
Unlock full access with a free 7-day trial
Transform your legal research with vLex
-
Complete access to the largest collection of common law case law on one platform
-
Generate AI case summaries that instantly highlight key legal issues
-
Advanced search capabilities with precise filtering and sorting options
-
Comprehensive legal content with documents across 100+ jurisdictions
-
Trusted by 2 million professionals including top global firms
-
Access AI-Powered Research with Vincent AI: Natural language queries with verified citations
Unlock full access with a free 7-day trial
Transform your legal research with vLex
-
Complete access to the largest collection of common law case law on one platform
-
Generate AI case summaries that instantly highlight key legal issues
-
Advanced search capabilities with precise filtering and sorting options
-
Comprehensive legal content with documents across 100+ jurisdictions
-
Trusted by 2 million professionals including top global firms
-
Access AI-Powered Research with Vincent AI: Natural language queries with verified citations