Liberty Insurance Ltd and Anor v EirGrid Plc

JurisdictionIreland
CourtHigh Court
JudgeMr. Justice Michael Quinn
Judgment Date02 April 2026
Neutral Citation[2026] IEHC 210
Docket NumberRECORD NO. 2017/7333P
Between
Liberty Insurance Limited

and

Snugborough Windfarm (Roi) Limited (In Liquidation)
Plaintiffs
and
Eirgrid Plc
Defendant

[2026] IEHC 210

RECORD NO. 2017/7333P

THE HIGH COURT

COMMERICAL

Penalty – Discrimination – Preliminary objections – Plaintiffs claiming that the contractual requirement for a bond and the amount of the bond amounted to a penalty which was unenforceable – Whether the defendant discriminated against the plaintiffs

Facts: The second plaintiff, Snugborough Windfarm (ROI) Ltd, on 29 October 2009, entered a Connection Agreement with the defendant, EirGrid plc, committing that it would construct an electricity generating facility at Ballakelly, County Louth, which would connect to the national grid. As security for that commitment, it procured that Quinn Insurance Ltd, the predecessor of the first plaintiff, Liberty Insurance Ltd, issue a bond in favour of the defendant. When the second plaintiff failed to construct the facility and connect to the grid, the defendant drew down the bond in its full amount of €4.45m, which the first plaintiff paid. The plaintiffs claimed that the contractual requirement for the bond and the amount of the bond amounted to a penalty which was unenforceable. They also claimed that in drawing down the bond the defendant discriminated against them in breach of the Electricity Regulation Act 1999 and the European Communities (Internal Market in Electricity) Regulations 2000. They claimed for recoupment of the bond amount paid over. The defendant denied that the law relating to penalties applied to the requirement for the bond, and denied that it discriminated unlawfully against the plaintiffs. It advanced a number of preliminary objections to the proceedings, including the Statute of Limitations, laches, estoppel, and claimed that if the bond requirement and its quantum were to be challenged the proper procedure was judicial review of relevant decisions and directions of its regulator, then the Commission for Energy Regulation and that the proceedings were a collateral attack to those decisions and distinctions.

Held by the High Court (Quinn J) that none of the preliminary objections were a bar to the two substantive claims pursued at the trial. He held that the purpose of the bond was to deter hoarding of capacity on the grid; it was not to deter breaches of individual connection agreements, and was not an unenforceable penalty. He held that the quantum of the bond was determined by a formula set by the Commission for Regulation of Utilities, whose decisions and directions to the defendant were not challenged, and could not be challenged in the proceedings. He held that the quantum of the bond was not, and was not required to be, set by reference to the components of Deep Reinforcement Works undertaken on the project, but was a function of the contracted capacity; it was not disproportionate or extravagant and when paid, it was not a ‘windfall’ in the hands of the defendant. He held that the allegation of unlawful discrimination was not made out. He held that the remedy sought in relation to discrimination namely a declaration that the demand on the bond was discriminatory and ultra vires must be refused; similarly this could not constitute a ground for any of the other declarations sought such as a declaration of unjust enrichment, a declaration that the sum of €4.45 million is held in trust for the benefit of the plaintiffs or that the plaintiffs are entitled to “an equitable charge over the assets of the defendant to the value of €4.45 million”.

Quinn J dismissed the action.

Action dismissed.

JUDGMENT of Mr. Justice Michael Quinn delivered on the 2 nd day of April 2026

Table of Contents

PART ONE: INTRODUCTION

3

Background

4

PART TWO: THE BALLAKELLY FACILITY

5

Termination of Connection Agreement and draw down of the bond

7

PART THREE: THESE PROCEEDINGS

9

PART FOUR: THE ACT, REGULATIONS, AND LICENCE OF THE DEFENDANT

14

Electricity Regulation Act 1999

14

European Communities (Internal Market in Electricity) Regulations, 2000

15

Memorandum of Association of the defendant

16

29 June 2006: Eirgrid Transmission System Operator Licence

17

PART FIVE: COMMISSION DECISIONS

18

19 December 2003 CER/03/298: Regulator Consultation on Structure of Tariffs

18

25 August 2009 CER/09/138, Decision Paper on Electricity Network Connection Policy

19

12 October 2016: CER/16/284: Connection Policy Transitional Arrangements (“the Amnesty”)

22

PART SIX: CHRONOLOGY

23

17 July 2008 Offer Letter

23

29 October 2009, Transmission Connection Agreement

27

July 2013: General Conditions

29

9 September 2008: The MEC bond

34

Events after the Connection Agreement

35

Termination of the Connection Agreement

38

Demand on the bond

39

PART SEVEN: THE PRELIMINARY OBJECTIONS

40

First Objection: Locus Standi

40

Subrogation

40

Assignment dated 10 August 2016

44

Second Objection: Statute of Limitations 1957

46

Third Objection: Laches

47

Fourth Objection: Connection Agreement validly terminated: Clause 3.2

50

Fifth Objection: Estoppel by Deed

52

Sixth Objection: Alternative Dispute Resolution

54

Seventh Objection: Collateral Attack/Abuse of Process

56

PART EIGHT: THE PENALTY CLAIM

61

Discussion

63

Nature of the Bond

65

Penalty Clauses Generally

69

The bond as a deterrent

73

The Purpose of the Bond

76

The Secondary Purpose

78

CER/09/138 25 August 2009: Decision on Electricity Network Connection Policy

83

Evidence of Mr. Mullan

85

Evidence of Mr. Thompson

87

Deep Reinforcement Works

90

Energy supply

94

Conclusion on the Penalty Claim

98

PART NINE: THE DISCRIMINATION CLAIM

98

12 October 2016: The Amnesty CER/16/284

100

Cuilleen and Suir

106

Ballakelly

108

The first plaintiff

113

Conclusion as regards discrimination

115

PART TEN: CONCLUSION

116

PART ONE: INTRODUCTION
1

. The Electricity Supply Board (ESB) is the owner of the electricity transmission and distribution network in the State. The grid infrastructure of the network is operated by the defendant, which is known as the transmission systems operator (“TSO”). The defendant is owned by the State and is responsible for the operation and development of the grid. It is regulated pursuant to the Electricity Regulation Act 1999 (“the Act”) as amended, and by the European Communities (Internal Market in Electricity) Regulations 2000 ( SI 445/2000) as amended, the “Regulations”.

2

. On 29 October 2009, the second named plaintiff entered a Connection Agreement with the defendant, committing that it would construct an electricity generating facility at Ballakelly, County Louth, which would connect to the national grid. As security for this commitment, it procured that the predecessor of the first plaintiff, Quinn Insurance Limited, issue a bond in favour of the defendant. When the second plaintiff failed to construct the facility and connect to the grid, the defendant drew down the bond in its full amount of €4.45m, which the first plaintiff paid. In these proceedings the plaintiffs claim that the contractual requirement for the bond and the amount of the bond amounted to a penalty which is unenforceable. They also claim that in drawing down the bond the defendant discriminated against them in breach of the Electricity Regulation Act 1999 and the European Communities (Internal Market in Electricity) Regulations 2000 ( SI 445/2000). They claim for recoupment of the bond amount paid over.

3

. The defendant denies that the law relating to penalties applies to the requirement for the bond, and denies that it discriminated unlawfully against the plaintiffs. It advances a number of preliminary objections to the proceedings, including the Statute of Limitations, laches, estoppel, and claim that if the bond requirement and its quantum were to be challenged the proper procedure was judicial review of relevant decisions and directions of its regulator, then the Commission for Energy Regulation and that these proceedings are a collateral attack to those decisions and distinctions.

Background
4

. The defendant is licensed by the Commission for Regulation of Utilities, formerly the Commission for Energy Regulation, to which I refer as the Commission. The Commission issues directions, decisions and authorisations to the defendant pursuant to the Act and the Regulations.

5

. A key function of the defendant is to manage the network of connections to the national grid, both from generators of power and from users and distributors. A central feature of this function is to receive applications for connections, to offer connection terms, and where offers are made and accepted, to enter into agreements, known as Connection Agreements for parties to connect to and use the transmission system. Connection Agreements govern the terms and conditions, including pricing, on which generators and others may connect.

6

. Each connection absorbs transmission capacity in the grid which is limited. Therefore, in determining the allocation of connections and the conditions of connections one of the important policies is to ensure that capacity in the network is not utilised or committed to parties whose applications are speculative or who ultimately are unable or fail to complete their projects and fail to deliver energy through their committed connection, thereby “hoarding” capacity that could have been availed of by other generators. To discourage such hoarding of network capacity one of the typical preconditions of Connection Agreements is that the applicant provide security for its commitment to proceed. The typical form of such security is the provision of a bond referred to as a Maximum Export Capacity Bond, an...

Get this document and AI-powered insights with a free trial of vLex and Vincent AI

Get Started for Free

Unlock full access with a free 7-day trial

Transform your legal research with vLex

  • Complete access to the largest collection of common law case law on one platform

  • Generate AI case summaries that instantly highlight key legal issues

  • Advanced search capabilities with precise filtering and sorting options

  • Comprehensive legal content with documents across 100+ jurisdictions

  • Trusted by 2 million professionals including top global firms

  • Access AI-Powered Research with Vincent AI: Natural language queries with verified citations

vLex

Unlock full access with a free 7-day trial

Transform your legal research with vLex

  • Complete access to the largest collection of common law case law on one platform

  • Generate AI case summaries that instantly highlight key legal issues

  • Advanced search capabilities with precise filtering and sorting options

  • Comprehensive legal content with documents across 100+ jurisdictions

  • Trusted by 2 million professionals including top global firms

  • Access AI-Powered Research with Vincent AI: Natural language queries with verified citations

vLex

Unlock full access with a free 7-day trial

Transform your legal research with vLex

  • Complete access to the largest collection of common law case law on one platform

  • Generate AI case summaries that instantly highlight key legal issues

  • Advanced search capabilities with precise filtering and sorting options

  • Comprehensive legal content with documents across 100+ jurisdictions

  • Trusted by 2 million professionals including top global firms

  • Access AI-Powered Research with Vincent AI: Natural language queries with verified citations

vLex

Unlock full access with a free 7-day trial

Transform your legal research with vLex

  • Complete access to the largest collection of common law case law on one platform

  • Generate AI case summaries that instantly highlight key legal issues

  • Advanced search capabilities with precise filtering and sorting options

  • Comprehensive legal content with documents across 100+ jurisdictions

  • Trusted by 2 million professionals including top global firms

  • Access AI-Powered Research with Vincent AI: Natural language queries with verified citations

vLex

Unlock full access with a free 7-day trial

Transform your legal research with vLex

  • Complete access to the largest collection of common law case law on one platform

  • Generate AI case summaries that instantly highlight key legal issues

  • Advanced search capabilities with precise filtering and sorting options

  • Comprehensive legal content with documents across 100+ jurisdictions

  • Trusted by 2 million professionals including top global firms

  • Access AI-Powered Research with Vincent AI: Natural language queries with verified citations

vLex

Unlock full access with a free 7-day trial

Transform your legal research with vLex

  • Complete access to the largest collection of common law case law on one platform

  • Generate AI case summaries that instantly highlight key legal issues

  • Advanced search capabilities with precise filtering and sorting options

  • Comprehensive legal content with documents across 100+ jurisdictions

  • Trusted by 2 million professionals including top global firms

  • Access AI-Powered Research with Vincent AI: Natural language queries with verified citations

vLex