Merchant Shipping (Safety of Fishing Vessels) (15-24 Metres) Regulations, 2007
Jurisdiction | Ireland |
Citation | IR SI 640/2007 |
ARRANGEMENT OF REGULATIONS |
PART 1 |
GENERAL |
1. Citation and commencement |
2. Application |
3. Definitions |
4. Exemptions and equivalents |
5. Maintenance and upkeep |
6. Repairs, alterations and modifications |
7. Surveys |
8. Surveyor's report and declaration of survey |
9. Fishing Vessel Safety Certificates and exemption certificates |
10. Duration of Fishing Vessel Safety Certificate |
11. Extension of Fishing Vessel Safety Certificate |
12. Cancellation of certificates and Cesser |
PART 2 |
CONSTRUCTION, WATERTIGHT INTEGRITY AND EQUIPMENT |
13. Construction |
14. Watertight doors |
15. Hull integrity |
16. Weathertight doors |
17. Hatchways closed by wood covers |
18. Hatchways closed by covers other than wood |
19. Machinery space openings |
20. Other deck openings |
21. Ventilators |
22. Air pipes |
23. Sounding devices |
24. Sidescuttles and windows |
25. Inlets and discharges |
26. Freeing ports |
27. Anchor and mooring equipment |
28. Working decks within an enclosed superstructure |
29. Tanks for fish in refrigerated (RSW) or chilled (CSW) sea water |
PART 3 |
STABILITY AND ASSOCIATED SEAWORTHINESS |
30. Stability |
31. Stability criteria |
32. Flooding of fish-holds |
33. Particular fishing methods |
34. Severe wind and rolling |
35. Water on deck |
36. Operating conditions |
37. Ice accretion |
38. Inclining test |
39. Stability information |
40. Portable fish-hold divisions |
41. Freeboard |
42. Maximum permissible operating draught |
PART 4 |
MACHINERY AND ELECTRICAL INSTALLATIONS |
43. Definitions |
44. General |
MACHINERY INSTALLATIONS |
45. Propulsion and auxiliary machinery |
46. Propeller shafts |
47. Gearboxes |
48. Remote control of propulsion machinery |
49. Communications between wheelhouse and machinery space |
50. Means of going astern |
51. Propeller and stern gear |
52. Controllable pitch propellers |
53. Boilers, feed systems and steam piping arrangements |
54. Air pressure systems |
55. Oil fuel, lubricating oil and other flammable oils — general |
56. Arrangements for oil fuel installations |
57. Arrangements for lubricating oil, hydraulic oil and other flammable oils |
58. Bilge systems |
59. Bilge alarms |
60. Exhaust systems |
61. Steering gear |
62. Refrigeration systems for the preservation of the catch |
63. Spare gear |
ELECTRICAL INSTALLATIONS |
64. General |
65. Main source of electrical power |
66. Emergency source of electrical power |
67. Distribution systems |
68. Cables. |
69. Accumulator (storage) batteries and associated charging equipment |
70. Precautions against shock, fire and other hazards of electrical origin |
71. Lighting systems |
72. Electric motors |
73. Lightning conductors |
PERIODICALLY UNATTENDED MACHINERY SPACES |
74. Fire prevention |
75. Protection against flooding |
76. Alarm system |
77. Special requirements for machinery, boiler and electrical installations |
78. Safety system |
PART 5 |
FIRE PROTECTION, FIRE DETECTION, FIRE EXTINCTION AND FIRE FIGHTING |
79. Definitions |
80. Fire protection — general |
81. Structural fire protection on vessels with hulls constructed of steel or other equivalent material |
82. Structural fire protection on vessels with hulls constructed of combustible materials |
83. Ventilation systems |
84. Space heaters |
85. Galley area |
86. Means for stopping machinery |
87. Oil fuel installations (cooking ranges and heating appliances) |
88. Liquefied petroleum gas installations (cooking ranges and heating appliances) |
89. Storage of flammable liquids, toxic liquids, toxic gases and compressed gases |
90. Means of escape and emergency exits |
91. Automatic fire alarm and fire detection systems |
92. Fire pumps |
93. Fire mains |
94. Fire hydrants, fire hoses & nozzles |
95. Portable fire extinguishers — general |
96. Portable fire extinguishers — vessel requirements |
97. Fire-extinguishing installations in machinery spaces |
98. Ready availability of fire-extinguishing appliances |
99. Cleanliness of machinery spaces |
100. Fire Control Plan |
101. Equivalence |
PART 6 |
PROTECTION OF THE CREW |
102. General protective measures |
103. Deck openings |
104. Bulwarks, rails and guards |
105. Stairways and ladders. |
106. Accommodation ladders and gangways |
107. Galleys |
108. Lighting in working spaces and areas |
109. Ventilation in working and storage spaces |
110. Dangerous areas |
111. Miscellaneous |
PART 7 |
LIFE-SAVING APPLIANCES AND ARRANGEMENTS |
112. Definitions |
113. Evaluation, testing and approval of life-saving appliances and arrangements |
114. Number and types of survival craft |
115. Availability and stowage of survival craft |
116. Embarkation into survival craft |
117. Lifejackets |
118. Immersion suits |
119. Lifebuoys |
120. Line throwing appliances |
121. Distress signals |
122. Radio life-saving appliances |
123. Radar transponders |
124. Retro-reflective materials on life-saving appliances |
125. Marking of lifeboats, rescue boats and liferafts |
126. Operational readiness, maintenance and inspections |
127. Miscellaneous |
PART 8 |
EMERGENCY PROCEDURES, MUSTERS AND DRILLS |
128. General emergency alarm system, muster list and emergency instructions |
129. Abandon ship training and drills |
130. Training in emergency procedures |
131. Inspections |
PART 9 |
RADIOCOMMUNICATIONS |
132. Definitions |
133. Exclusions from Part 9 |
134. Equivalents and exemptions. |
135. Functional requirements. |
136. Installation, location and control of radio equipment |
137. Radio equipment to be provided for all sea areas |
138. Additional radio equipment to be provided for sea areas A1 and A2 |
139. Additional radio equipment to be provided for sea areas A1, A2 and A3 |
140. Radio watches |
141. Sources of energy |
142. Performance standards |
143. Serviceability and maintenance requirements |
144. Radio personnel |
145. Radio records |
PART 10 |
SHIPBORNE NAVIGATIONAL EQUIPMENT AND ARRANGEMENTS |
146. Shipborne navigational equipment |
147. Nautical instruments and publications |
148. Signalling equipment |
149. Navigating bridge visibility |
PART 11 |
CREW ACCOMMODATION |
150. General |
151. Lighting, heating and ventilation |
152. Sleeping rooms |
153. Mess rooms |
154. Sanitary facilities |
155. Potable water facilities |
156. Provision stores |
157. Cooking facilities |
SCHEDULE 1 |
CERTIFICATES AND RECORD OF EQUIPMENT FISHING VESSEL SAFETY CERTIFICATEFISHING VESSEL EXEMPTION CERTIFICATERECORD OF EQUIPMENT |
SCHEDULE 2 |
RECOMMENDED PRACTICE FOR ANCHOR AND MOORING EQUIPMENT |
SCHEDULE 3 |
INFORMATION AS TO STABILITY OF FISHING VESSELS |
SCHEDULE 4 |
AMMONIA REFRIGERATION SYSTEMS IN MANNED SPACES |
SCHEDULE 5 |
RADIO EQUIPMENT TESTS AND RESERVE POWER CHECKS |
SCHEDULE 6 |
RADIO LOG |
SCHEDULE 7 |
PUBLICATIONS, DIRECTIONS AND INFORMATION |
S.I. No. 640 of 2007 |
MERCHANT SHIPPING (SAFETY OF FISHING VESSELS) (15-24 METRES) REGULATIONS 2007 |
Notice of the making of this Statutory Instrument was published in |
“Iris Oifigiúil” of 21st September, 2007. |
I, NOEL DEMPSEY, Minister for Transport, in exercise of the powers conferred on me by section 19 (inserted by section 47 of the Maritime Safety Act 2005 (No. 11 of 2005)) of the Merchant Shipping Act 1992 (No. 2 of 1992) and the Maritime Transport, Safety and Security (Transfer of Departmental Administration and Ministerial Functions) Order 2005 ( S.I. No. 842 of 2005 ), hereby make the following regulations: |
PART 1 |
GENERAL |
Citation and commencement. |
1. (1) These Regulations may be cited as the Merchant Shipping (Safety of Fishing Vessels) (15-24 Metres) Regulations 2007. |
(2) These Regulations come into operation— |
(a) on 1 October 2007, for new vessels, |
(b) on 1 October 2008, for existing vessels the keel of which was laid or which was at a similar stage of construction on or after 1 October 1997, |
(c) on 1 October 2009, for existing vessels the keel of which was laid or which was at a similar stage of construction on or after 1 October 1987, and |
(d) on 1 October 2010, for existing vessels the keel of which was laid or which was at a similar stage of construction before 1 October 1987. |
Application. |
2. These Regulations apply to every mechanically propelled fishing vessel of 15 metres in length overall (L oa ) and over but less than 24 metres in length (L), registered in the State. |
Definitions. |
3. In these Regulations— |
“amidships” means the mid-length of L; |
“approved” means approved by the Minister, or approved in accordance with the standards as set out in the European Communities (Marine Equipment) Regulations 2003 ( S.I. No. 38 of 2003 ); |
“authorised officer” means— |
(a) a surveyor of ships under section 724 of the Merchant Shipping Act 1894 or a recognised organisation; or |
(b) a person, appointed under Regulation 7(11); |
“baseline” means the horizontal line intersecting at amidships the keel line; |
“breadth (B)” means the maximum breadth of the vessel, measured amidships to the moulded line of the frame in a vessel with a metal shell and to the outer surface of the hull in a vessel with a shell of any other material; |
“collision bulkhead” means a watertight bulkhead up to the working deck in the forepart of the vessel, which meets the following conditions— |
(a) the bulkhead shall be located at a distance from the forward perpendicular not less than 0.05L+0.8m and not more than 0.05L+1.35m, except as may be allowed by the Minister, |
(b) where any part of the underwater body extends forward of the forward perpendicular, for example a bulbous bow, the distance stipulated in paragraph (a) of this definition shall be measured from a point at mid-length of the extension forward of the forward perpendicular or from a point 0.015(L) forward of the forward perpendicular, whichever is less, and |
(c) the bulkhead may have steps or recesses provided they are within the limits specified in paragraph (a); |
“crew” means the skipper and all persons employed or engaged in any capacity on board a vessel on the business of... |
To continue reading