People Over Wind and Another v an Bord Pleanála and Others
Jurisdiction | Ireland |
Judge | Mr. Justice Haughton |
Judgment Date | 01 May 2015 |
Neutral Citation | [2015] IEHC 271 |
Court | High Court |
Date | 01 May 2015 |
BETWEEN
AND
AND
[2015] IEHC 271
THE HIGH COURT
Environment – Order of certiorari – Planning and Development Act 2000 – Planning permission – Environmental Impact Assessment.
Facts: The applicant sought for an order of certiorari quashing the decision of the respondent granting permission for a development of an 18-turbine wind farm. The applicant questioned the adequacy of the Environmental Impact Statement. The applicant alleged that there was failure to properly record a determination and to carry out a Proper Appropriate Assessment.
Mr. Justice Haughton held that the application for an order of certiorari quashing the decision of the respondent granting permission for a development of an 18-turbine wind farm would be denied and therefore, accordingly the application would be dismissed. The Court held that the there was no significant lacunae and there was no failure to properly record a determination and to carry out a Proper Appropriate Assessment on the part of the respondent. The Court held that the law required the satisfaction of the decision maker. The Court held that the respondent had ample evidence before it and it reasonably concluded that the proposed development had not adversely affected any integrity.
JUDGMENT of Mr. Justice Haughton delivered the 1st day of May, 2015
Index | Paragraphs |
Introduction | 1 - 6 |
Order Granting Leave | 7 - 10 |
Scope of Judicial Review - Grid Connection | 11 - 52 |
- Decision of the Court | 53 - 60 |
Ground (3) - Adequacy of the Environmental Impact Statement | 61 - 97 |
- Decision of the Court | 98 - 101 |
Recording and Adequacy of the Environmental Impact Assessment | 102 - 105 |
- Did the Board carry out an Environmental Impact Assessment 106 - 112 | - Decision on whether the Board carried out an Environmental |
- Impact Assessment | 113 - 117 |
- Visual Impact | 118 - 125 |
- Noise Impact | 126 - 133 |
- Shadow Flicker | 134 - 137 |
- Haul Routes | 138 - 146 |
Failure to Properly Record Determination | 147 - 154 |
Failure to Carry out a Proper Appropriate Assessment | 155 |
- Legislative Background | 156 - 161 |
- Background Facts Relating to Appropriate Assessment | 162 - 194 |
- The Board's Decision on Appropriate Assessment | 195 - 199 |
- The Applicants' Submissions | 200 - 204 |
- Dr. Moorkens and the Best Scientific Evidence | 205 - 213 |
- Submissions of the Respondent and Coillte | 214 - 221 |
- Discussion | 222 - 257 |
- Decision of the Court | 258 - 267 |
Ground (6) - Contravention of Development Plan | 268 - 272 |
Other Grounds | 273 - 277 |
Conclusion | 278 |
1. In this application for judicial review the applicants seek an order of certiorari quashing the decision, dated 13 th June, 2014, of the respondent, An Bord Pleanala ("the Board" or "the respondent") to grant permission to the second named Notice Party ("Coillte") in respect of the proposed development of an 18 turbine wind farm at Cullenagh, County Laois.
2. The first named applicant is a committee comprising representatives of some 70 concerned households in the area of the proposed development and it made observations/submissions in respect of the initial application for permission to Laois County Council and in respect of the appeal from the planning authority's decision to the respondent.
3. The second named applicant is a non-governmental environmental organisation established for the purposes of protecting the environment at Ballyroan, Co. Laois and the surrounding townlands. The second named applicant also objected to the planning application and made submissions/observations at the appeal stage.
4. The factual background is as follows. Coillte applied for planning permission for a development of an 18 turbine windfarm near Cullenagh, Co. Laois on 9 th August, 2013 which was accompanied by an Environmental Impact Statement ("EIS") and a Natura Impact Statement ("NIS"). The proposed development included inter alia construction of a permanent meteorological mast, a single story 38kv substation with sanitary facilities and parking spaces, underground cabling and strengthening and widening of roads to be used during the construction and operation phases of the development. Members of the public, including the applicants and a number of public bodies and persons made submissions in relation to the application. On 1 st October, 2013, officials of a number of departments of Laois County Council also submitted reports on the application.
5. On 2 nd October, 2013, Laois County Council planning authority refused permission for the development on the basis that appropriate or adequate consideration had not been given to the effects of the development on the environment in the EIS or the NIS. The reasons for refusal are considered more fully below. Coillte then appealed the decision to the Board. Further information was provided to the Board by Coillte in relation to the development following the application. Ms. Joanne Kelly was appointed inspector and was tasked with producing a report on the proposed development which was completed on 11 th February, 2014. The Board, after examining the information before it granted permission for the development on 13 th June, 2014. The applicants later applied to the Court for judicial review of the Board's decision.
6. These proceedings were heard on affidavit in the Commercial Court.
7. By order of Ms. Justice Baker made on 31 st July, 2014, leave was granted on grounds (2)-(14) to seek an order of certiorari quashing the Board's decision granting permission for the proposed development along with any such further orders as the Court deems meet and the costs of the application for judicial review.
8. For completeness, grounds (1)-(14), delineated in para. (E) of the Statement Required to Ground an Application for Judicial Review, are outlined below:-
2 "(1) The respondent failed to carry out a proper environmental impact assessment (EIA) as required under national and European Law.
(2) The respondent failed to carry out a proper appropriate assessment (AA) as required under National and European Law.
(3) The respondent had before it an environmental impact statement (EIS) that was inadequate in that it failed to properly describe the proposed development and its effects and contained material that was inaccurate and incorrect. Accordingly no or no lawful EIA was or could have been conducted.
(4) The respondent had before it a natura impact statement (NIS) that was inadequate as it did not properly describe the proposed development or its effects on nearby European Sites. The planning authority and the notice party (the Department of Arts, Heritage and the Gaeltacht) identified significant lacunae in the information provided by the notice party developer, Coillte Teoranta. These lacunae were never satisfactorily addressed. Accordingly no, or no lawful AA was or could have been conducted.
(5) The respondent failed to properly record its determination and failed to give any or any proper reasons for its determination contrary to National and European Law.
(6) The respondent failed to have regard for the decision to refuse permission for the development by Laois County Council. The Council found that the proposed development would contravene development objective NH13/001 of the Laois County Development Plan 2011-2017 pursuant to s.37(2) of the Planning and Development Act 2000 the Board may only grant planning permission where permission has been refused by reason of material contravention of a development plan in specified limited circumstances. The Board had no regard to this section or its applicability to the decision of the planning authority. The said decision is ultra vires, void and of no legal effect.
(7) The applicant herein raised a request for information pursuant to the European Communities (Access to Information on the Environment) Regulations 2007 requesting a copy of the record of the environmental impact assessment and appropriate assessment carried out. The applicant received a response on 18 th July 2014. This response stated that the EIA and AA conducted comprised all of the documents received during the course of the appeal. The respondent was unable to furnish, or direct the applicant to, any particular record of the assessment. This is contrary to the requirements of European Law.
(8) The respondent has nowhere produced an assessment of the development for the purposes of the EIA and Habitats Directive. The record in the Board's direction and decision is perfunctory and uninformative. It gives no proper account of the assessment undertaken. In particular, it fails entirely to engage with the decision of the planning authority. It also fails to engage with the recommendations and concerns of the officers of the planning authority and the Department of Arts Heritage and the Gaeltacht in the course of the consideration of the planning application and the identified deficiencies in respect of the information provided by the applicant for permission. These concerns were expressed again in the context of the appeal and were echoed by the applicants and the public concerned. The decision is contrary to law.
(9) The Board failed to require the submission of a proper revised EIS and...
To continue reading
Request your trial-
Stapleton v an Bord Pleanála and Others
...Four Districts Woodland Habitat Group v. An Bord Pleanála [2023] IEHC 335. 362 People Over Wind & Anor v. An Bord Pleanála & Ors (No. 1) [2015] IEHC 271. 363 O'Donnell v. An Bord Pleanála & Drumakilla [2023] IEHC 364 Note: this approach is not intended to dilute the insistence on pleading i......
-
An Taisce The National Trust for Ireland v The Minister for Housing, Local Government and Heritage and Others
...the application for judicial review and on the court.’ (Emphasis added). ‘In People Over Wind and Another v an Bord Pleanála and Others [2015] IEHC 271, Haughton J stated that (§55) in assessing the scope of the Statement of Grounds the approach that should be adopted is that of a ‘ fair an......
-
Joyce Kemper v an Bord Pleanala
...Bord Pleanála [2019] IEHC 929, which in turn borrowed heavily from the judgment of Haughton J. in People Over Wind v. An Bord Pleanála [2015] IEHC 271:- “76. This is an application for judicial review and it is important to recall the role of the court on such an application. In so far as a......
-
Coyne and Another v an Bord Pleanála and Others; Coyne and Another v an Bord Pleanála and Others
...doubt searches of slightly different phrases to the same effect would have added to that number. 26 People over Wind v An Bord Pleanála [2015] IEHC 271 §120; Tristor v Minister for Environment & Ors [2010] IEHC 397 §§5.4 & 6.6 — in §6.6 citing Dellway & McKillen v The National Asset Managem......