Donegal County Council v Planree Ltd and Another
Jurisdiction | Ireland |
Judge | Mr Justice David Holland |
Judgment Date | 10 April 2024 |
Neutral Citation | [2024] IEHC 193 |
Court | High Court |
Docket Number | 2023/96 MCA |
In the Matter of Section 160 of the Planning and Development Act 2000
and
[2024] IEHC 193
2023/96 MCA
THE HIGH COURT
PLANNING AND ENVIRONMENT
JUDGMENT OFMr Justice David HollandDELIVERED 10 APRIL 2024.
INTRODUCTION | 3 |
The Dispute — Essentials | 4 |
The Site And Its Environmental Sensitivity | 6 |
PEAT SLIDES & AFTERMATH | 8 |
THE DEVIATIONS | 13 |
Table — List of Deviations | 14 |
The Red Line Issue | 25 |
SUBSTITUTE CONSENT APPLICATION FOR DEVIATIONS & APPROVAL OF REMEDIATION OF PEAT SLIDE | 26 |
S.160 MOTION, S.160 & THE CONCEPT OF UNAUTHORISED DEVELOPMENT | 28 |
Unauthorised Development — Concept & Significance | 30 |
MATERIALITY & UBIQUITY OF DEVIATIONS | 31 |
IDENTIFICATION OF THE UNAUTHORISED DEVELOPMENT — ANAYSIS & DECISION | 37 |
The Issue | 37 |
Analysis | 38 |
The SID Permission | 39 |
Some Caselaw | 40 |
Are the Material Deviations severable from the Windfarm? | 49 |
In What Would Completion of the Windfarm result? | 50 |
Decision — identification of unauthorised development | 50 |
Alternative Decision — Interpretation of S.160 | 50 |
EIA & AA — TIMING, REMEDIAL EIA & AA & SUBSTITUTE CONSENT | 51 |
EU Law | 52 |
Irish law — Substitute Consent | 56 |
Activity Cessation Orders | 59 |
The Board's Decision To Grant Leave To Seek Substitute Consent & Options Open to Planree | 62 |
SCOPE OF S.160 & DISCRETIONARY FACTORS | 67 |
Introduction | 67 |
Possible Orders | 68 |
Onus of proof | 69 |
Discretionary factors | 70 |
General Observations | 70 |
The integrity of the systems of planning and environmental law. | 71 |
Other Factors | 76 |
The presence/absence of a likelihood of adverse environmental effect. | 77 |
Proportionality & the Precautionary Principle | 78 |
THE EXPERT EVIDENCE | 78 |
DISCRETION — ANALYSIS & DECISION | 82 |
Remediation Order | 82 |
What is at stake? | 84 |
The Substitute Consent Application | 84 |
Discretionary Considerations | 85 |
The Nature of the Breaches | 85 |
Planree's Conduct | 85 |
Public Interest — Integrity of the Systems of Planning And Environmental Law. | 88 |
Public Interest — Wind Energy Projects | 90 |
Attitude of the Planning Authority | 92 |
Planree's Circumstances, Hardship and Consequences of the Order — Alleged Prospect of Insolvency & Lesser Financial Detriment | 93 |
Do the Remaining Works Affect or Exacerbate any Environmental Risk Posed by The Deviations? | 97 |
Proportionality & the Precautionary Principle | 98 |
A Limited Order? | 100 |
The Board's exercise of its s.177J Jurisdiction & Liberty to Apply | 100 |
Conclusion — Discretion & Orders | 101 |
The Applicant (“Donegal CC”) as planning authority seeks injunctions pursuant to Section 160 of the Planning and Development Act 2000 (“s.160” and “PDA 2000”) restraining the Respondents (“Planree” and “Mid-Cork Electrical”) from further development of a 90mw 1 19-turbine windfarm (the “Windfarm” and “Meenbog Windfarm”) on a site of 990 hectares at the Barnesmore Gap, in the townlands of Meenbog, Croaghonagh and Cashelnavean, County
Donegal 2 (“the Site”) which entire Windfarm, Donegal CC asserts, is by reason of numerous material deviations (the “Material Deviations”) from the applicable planning permission, unauthorised development within the meaning of the PDA 2000Planree's Meenbog Windfarm has been in gestation since at least 2013.3 Mid-Cork Electrical is its contractor for the construction of the Windfarm. They are associated entities – I am unaware of the details but Michael Murnane is a director of both and is a deponent for both. Save where necessary, I will refer to them collectively sub nom “Planree”.
Planree has an SID Planning Permission 4 (“the SID Permission”) dated 25 June 2018 for the Windfarm. It was amended in June 2019 by decision of the Board under s.146B PDA 2000, essentially allowing bigger turbines/longer rotor blades. By the SID Permission, the Windfarm is to be constructed within 10 years of 25 June 2018 and may operate for 25 years from its first commissioning. Due to the nature of Windfarm, the particular environmental sensitivity of the Site and their proximity to Natura 2000 sites, including an adjoining SAC, 5 the decision to grant the SID Permission was informed by both EIA 6 and AA.7 Condition 1 to the Permission is in the usual form requiring completion of the project in accordance with the plans and particulars lodged. Condition 7 required full implementation of all construction methods and environmental mitigation measures, including operation monitoring requirements, as set out in the EIAR 8 and the CEMP.9
Planree says, variously, that about “90%” and “95%” of the groundworks are complete.10 I lay little store in such percentages as mathematical assertions but accept that the Windfarm is at a very advanced stage of construction. Views differ as to whether the outstanding groundworks 11 are minor or significant. Thereafter, the main remaining element of the works is the installation of the turbines and rotors – which are in storage in nearby Killybegs.
Donegal CC asserts, in essence, that:
• By reason of the Material Deviations, the entire Windfarm is unauthorised development as one not in conformity with the SID Permission.
• As matters stand, as a matter of planning law, and pending any regularisation of that unauthorised status, the Windfarm can no longer be completed in conformity with the SID Permission.
• As a matter of environmental law, it is concerned as to the environmental effects of building out and operation of the Windfarm – given the Material Deviations have not been subjected to EIA Screening and AA.
• Accordingly, to permit the building out and operation of the Windfarm would be to undermine the integrity of the planning and environmental law systems and allow Planree to profit from its wrong in effecting the Material Deviations.
• It seeks, by this s.160 motion, to restrain all further works until, at least, the outcome of the Substitute Consent 12 process.
Planree's essential position is that it:
• Accepts that there are numerous deviations from the applicable planning permission.
• Now accepts that they are material deviations which constitute unauthorised development – not least as the Board has determined that they require EIA Screening and AA.
• Will make a Substitute Consent application to the Board to regularise the status of those deviations. That may take some years given backlogs in the Board in processing such applications.
• Should be allowed to build out the remaining, authorised, elements of the Windfarm and operate it pending the Board's decision on Substitute Consent.
Planree's position is argued, in essence, on the following bases:
• The Material Deviations are unauthorised development but do not render the entire Windfarm unauthorised.
• The Windfarm can now be built out in conformity with the Planning Permission as all remaining works conform to the relevant SID Permission.13
• Accordingly, there is no jurisdiction to injunct the completion and operation of the Windfarm.
○ This a “curate's egg” argument: that the Windfarm is authorised “in parts” and that I can injunct only the unauthorised parts.
• Alternatively, and even if the entire Windfarm is unauthorised development, I should exercise my discretion against an injunction.
The parties dispute whether to build out the remaining elements of the Windfarm would represent significant environmental risk unassessed in EIA Screening and AA.
As I have said, Planree now agrees that it has materially deviated from the scope of development permitted by the SID Permission. It has obtained leave to seek Substitute Consent for those Material Deviations and will make the Substitute Consent application presently.14 However, it fears delay of perhaps years in the Board's deciding that application and financial losses in that interim. The crux of the case, in reality, is that it wants, meanwhile, to build out and operate its Windfarm, whereas Donegal CC seeks, by this s.160 motion, to restrain all further works until, at least, the outcome of the Substitute Consent process.
In consequence, the precise identification of the unauthorised works is disputed – not as to whether the Material Deviations are unauthorised (it is agreed that they are) – but as to whether they, as it were, infect the planning status of the remainder of Windfarm on the basis that the development permitted must be considered as a whole. This is a question on which authority is surprisingly sparse.
The foregoing may oversimplify a complex dispute but indicates the main battlelines.
The Site is in an upland rural area characterised by a mix of mountains, blanket bog, forestry and agricultural fields. The Site itself is mainly in coniferous forestry on upland blanket bog. It includes the hills of Barnsmore (451m), Croaghanagh (433m), Cross Hill (350m) and Carrickaduff Hill (329m) and parts of five valleys, each drained as follows: 15
• The first valley is drained by Mary Breen's Burn, on to the Mourne Beg River, the River Derg, and the Mourne River which flows into the River Finn SAC and the River Foyle and Tributaries SAC (NI 16).
• The second valley is drained by the Bunadaowen River, several tributaries, and a network of small forest drains. The Bunadaowen River also joins the Mourne Beg which, as stated above, ultimately flows into the River Finn SAC and the River Foyle and Tributaries SAC (NI).
• The third valley is drained by the Shruhangarve Stream and a tributary. The Shuhangarve also joins the Mourne Beg which, as stated above, ultimately flows into the River Finn...
To continue reading
Request your trialUnlock full access with a free 7-day trial
Transform your legal research with vLex
-
Complete access to the largest collection of common law case law on one platform
-
Generate AI case summaries that instantly highlight key legal issues
-
Advanced search capabilities with precise filtering and sorting options
-
Comprehensive legal content with documents across 100+ jurisdictions
-
Trusted by 2 million professionals including top global firms
-
Access AI-Powered Research with Vincent AI: Natural language queries with verified citations

Unlock full access with a free 7-day trial
Transform your legal research with vLex
-
Complete access to the largest collection of common law case law on one platform
-
Generate AI case summaries that instantly highlight key legal issues
-
Advanced search capabilities with precise filtering and sorting options
-
Comprehensive legal content with documents across 100+ jurisdictions
-
Trusted by 2 million professionals including top global firms
-
Access AI-Powered Research with Vincent AI: Natural language queries with verified citations

Unlock full access with a free 7-day trial
Transform your legal research with vLex
-
Complete access to the largest collection of common law case law on one platform
-
Generate AI case summaries that instantly highlight key legal issues
-
Advanced search capabilities with precise filtering and sorting options
-
Comprehensive legal content with documents across 100+ jurisdictions
-
Trusted by 2 million professionals including top global firms
-
Access AI-Powered Research with Vincent AI: Natural language queries with verified citations

Unlock full access with a free 7-day trial
Transform your legal research with vLex
-
Complete access to the largest collection of common law case law on one platform
-
Generate AI case summaries that instantly highlight key legal issues
-
Advanced search capabilities with precise filtering and sorting options
-
Comprehensive legal content with documents across 100+ jurisdictions
-
Trusted by 2 million professionals including top global firms
-
Access AI-Powered Research with Vincent AI: Natural language queries with verified citations

Unlock full access with a free 7-day trial
Transform your legal research with vLex
-
Complete access to the largest collection of common law case law on one platform
-
Generate AI case summaries that instantly highlight key legal issues
-
Advanced search capabilities with precise filtering and sorting options
-
Comprehensive legal content with documents across 100+ jurisdictions
-
Trusted by 2 million professionals including top global firms
-
Access AI-Powered Research with Vincent AI: Natural language queries with verified citations
