VA96.4.016 & VA96.4.017&VA93.4.015 & VA93.4.016 – East Link Ltd.

Appeal NumberVA96.4.016 & VA96.4.017&VA93.4.015 & VA93.4.016
Year1998
Date11 May 1998
CourtValuation Tribunal
RespondentCommissioner of Valuation
AppellantEast Link Ltd.
Appeal No. VA96/4/016 &
VA96/4/017 ; VA93/4/015 &
VA93/4/016
AN BINSE LUACHÁLA
VALUATION TRIBUNAL
AN tACHT LUACHÁLA, 1988
VALUATION ACT, 1988
East Link Ltd. APPELLANT
and
Commissioner of Valuation RESPONDENT
RE: Tolls of Toll Road (pt. of) & Advertising Stations at
VA93/4/015 - York Road, Ward: Pembroke East A,
VA96/4/016 - York Road, Ward: Pembroke East A,
Tolls of Toll Road (pt. of) at
VA93/4/016 - (Easement), Ward: North Dock B,
VA96/4/017 - (Easement), Ward: North Dock B2, County Borough of Dublin
Rateable Occupation and quantum
B E F O R E
Liam McKechnie - Senior Counsel Chairman
Con Guiney - Barrister at Law Deputy Chairman
Barry Smyth - FRICS.FSCS Member
JUDGMENT OF THE VALUATION TRIBUNAL
ISSUED ON THE 11TH DAY OF MAY, 1998
By Notices of Appeal dated respectively 1st day of November 1993 and the 12th day of August
1996, the Appellant Company appealed against the determinations of the Commissioner of
Valuation in fixing the following rateable valuations on the above described hereditaments:-
2
VA93/4/015 - £4,750
Results of first appeal - 5th day of October 1993
VA93/4/016 - £250
VA96/4/016 - £10,260
Results of first appeal - 29th day of July 1996
VA96/4/017 - £540
Background:-
1. The background setting giving rise to these appeals lies in the enactment of the
Local Government (Toll Roads) Act 1979 the relevant provisions of which, for the
purposes of this judgement are, as follows:-
(a) Section 2 of this Act empowers a Road Authority, within its administrative
area, to charge and collect tolls in respect of the use of a toll road and to
provide and maintain ancillary buildings and structures,
(b) Under Section 3 each such authority has the power to make a scheme for the
establishment of a system of tolls in respect of the use of any public road
(Toll Scheme). That scheme when made, must be submitted to the Minister
for the Environment who may approve of the toll scheme with or without
modifications or who may refuse to approve it,
(c) Under Section 5, bye-laws can be made for the purposes of the operational
management of any such toll road and,
(d) Under Section 9 where a Toll Scheme has been approved by the Minister, a
Road Authority may enter into an agreement with any other person or body
for all or any of the purposes as specified in sub-sections 1 and 2 thereof.
These purposes cover the actual provision of toll roads, ancillary structures
and the cost thereof, the cost of maintenance and improvement, the making,
levying and collection of the tolls and amount thereof and finally the
application of the proceeds of such tolls.
It was under and pursuant to the provisions of this Act that the agreement next
hereinafter mentioned was entered into and executed by the parties thereto.